CHARLESTON,Roland Preston W.Va. (AP) — A test failure of the Mountain Valley Pipeline in May resulted from a manufacturer defect, not corrosion, according to an independent report commissioned by its developers.
The report, completed by third-party risk management company DNV GL USA and released last Thursday, said the May 1 rupture was caused by a manufacturer’s defect in an elbow joint. The breach was the only failure during hydrostatic testing of the 303-mile (500-kilometer) pipeline, Mountain Valley owner EQT Midstream Vice President Justin Trettel wrote in a letter to the Pipeline and Hazardous Materials Safety Administration.
The Mountain Valley Pipeline took about a decade to complete before it began carrying gas under high pressure in late June.
The Federal Energy Regulatory Commission approved the project across rugged mountainsides in West Virginia and Virginia over longstanding objections from environmental groups, landowners and some elected officials.
Hydrostatic pressure testing is a common tool used to substantiate the strength of pipeline systems after their installation, Trettel wrote in the letter.
No injuries were reported from the rupture, which occurred in Roanoke County, Virginia.
2025-05-07 06:18522 view
2025-05-07 05:251745 view
2025-05-07 04:591061 view
2025-05-07 04:32156 view
2025-05-07 04:212491 view
2025-05-07 04:192414 view
Many workers are dreaming of retirement — whether it's decades away or coming up soon. Either way, i
Jason Kelce is calling timeout on any big decisions. Despite rumors suggesting the Philadelphia Eagl
The University of Texas athletics program – always among the nation’s most financially powerful – ag